Skip to content
Gridcensus

Greenfield (NORTHERN NECK - UNKNOWN400303)

Greenfield

Richmond, Virginia · PJM

DC Readiness
45.2
Fair / 100

Greenfield (NORTHERN NECK - UNKNOWN400303) is a greenfield datacenter candidate site in Richmond, Virginia, interconnecting through PJM. It screens at 45.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationNORTHERN NECK
Substation voltage115 kV
Available capacity100 MW

Speed to power

ISO / RTO regionPJM
Queue depth878
Avg queue wait3.8 yrs

Connectivity

Nearest IXPQTS Richmond (RIC1)
IXP distance44.7 mi
Fiber providers2
Fiber coverage45.2%

Site characteristics

Site typeGreenfield

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterBank of America Data Center
DC distance44.0 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.33¢/kWh
Industrial electricity4.19¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$3,544

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 5 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
38
Fiber connectivity12%
25
Energy cost10%
50
Water risk8%
88
Natural hazard8%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Richmond, ranked by DC Readiness.

Sites near Greenfield (NORTHERN NECK - UNKNOWN400303)
SiteTypeVoltageCapacityQueue waitScore
DUNNSVILLESubstation-Adjacent230 kV300 MW3.8 yrs55.9
WESTMORELANDSubstation-Adjacent230 kV300 MW3.8 yrs55.9
NORTHERN NECKSubstation-Adjacent230 kV300 MW3.8 yrs55.9
Warsaw Buy Rite BuildingShovel-Ready3.8 yrs47.9
Richmond County Commerce CenterShovel-Ready3.8 yrs47.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (NORTHERN NECK - UNKNOWN400303), Richmond. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.