UNKNOWN121549

Substation-Adjacent

Greene, Virginia · PJM

DC Readiness
71.1
Excellent / 100

UNKNOWN121549 is a substation-adjacent datacenter candidate site in Greene, Virginia, interconnecting through PJM. It screens at 71.1/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN121549
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
LMP zonePJM_APS
Wholesale LMP$43.66/MWh
Utility commercial rate0.08¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth118
Avg queue wait3.0 yrs
Recent queue wait4.0 yrs
Completion rate23%
Withdrawal rate77%

Connectivity

Nearest IXPEquinix CU1/CU2/CU3/CU4 - Culpeper
IXP distance30.6 mi
Fiber providers4
Fiber coverage38.7%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance78.3 mi

Site characteristics

Parcel ownerVIRGINIA ELECTRIC & POWER CO
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteINTELLIGENT PLATFORMS LLC
Hazard sub-score60/100
Construction cost index62.4 (avg 100)

Location context

Nearest datacenterEquinix CU2
DC distance30.6 mi
Nearest rail2.7 mi
Nearest gas pipeline3.4 mi
Nearest fiber route28.5 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.73¢/kWh
Industrial electricity6.05¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$8,303

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
53
Fiber connectivity12%
59
Energy cost10%
81
Water risk8%
88
Natural hazard8%
60
Buildability7%
92
Labor market4%
50
DC cluster4%
70
Land / acreage3%
46
Construction cost3%
98
Gas pipeline2%
89
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Greene, ranked by DC Readiness.

Sites near UNKNOWN121549
SiteTypeVoltageCapacityQueue waitScore
ELKTON D.P.Substation-Adjacent115 kV100 MW3.0 yrs68.2
ElktonBrownfield1 MW3.1 yrs59.7
Davis Lamb PropertyShovel-Ready49.3
RT 33 PropertyShovel-Ready48.9
Enterprise Pointe / Oliver PropertyShovel-Ready48.7
Tennyson PropertyShovel-Ready48.5
27 & 29 Industrial DriveShovel-Ready48.5
Spotswood Business Park L 10Shovel-Ready48.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN121549, Greene. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.