Greenfield (BORDEN CO - None)

Greenfield

Borden County, Texas · ERCOT

DC Readiness
53.2
Fair / 100

Greenfield (BORDEN CO - None) is a greenfield datacenter candidate site in Borden County, Texas, interconnecting through ERCOT. It screens at 53.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBORDEN CO
Substation voltage138 kV
Available capacity100 MW
LMP zoneERCOT_WEST
Wholesale LMP$14.46/MWh
Utility commercial rate0.08¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Fiber providers3
Fiber coverage54.1%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance279.6 mi

Site characteristics

Site typeGreenfield
Parcel ownerONCOR ELECTRIC DELIVERY CO.
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score45/100
Construction cost index103.6 (avg 100)

Location context

Nearest datacenterAligned Lubbock
DC distance71.8 mi
Nearest rail22.4 mi
Nearest gas pipeline1.4 mi
Nearest fiber route14.1 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.19¢/kWh
Industrial electricity10.35¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$1,141

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
59
Fiber connectivity12%
51
Energy cost10%
93
Water risk8%
54
Natural hazard8%
45
Buildability7%
70
Labor market4%
50
DC cluster4%
20
Land / acreage3%
54
Construction cost3%
64
Gas pipeline2%
96
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Borden County, ranked by DC Readiness.

Sites near Greenfield (BORDEN CO - None)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN305803Substation-Adjacent345 kV600 MW3.4 yrs67.8
UNKNOWN302823Substation-Adjacent345 kV600 MW3.4 yrs62.6
Greenfield (SCURRY - UNKNOWN302823)Greenfield345 kV600 MW3.4 yrs59.5
Greenfield (UNKNOWN302823 - SCURRY)Greenfield345 kV600 MW3.4 yrs59.5
Greenfield (SCURRY - UNKNOWN302823)Greenfield345 kV600 MW3.4 yrs59.4
Greenfield (UNKNOWN305803 - UNKNOWN302823)Greenfield345 kV600 MW3.4 yrs59.4
Greenfield (UNKNOWN304833 - UNKNOWN305803)Greenfield345 kV600 MW3.4 yrs59.0
Greenfield (UNKNOWN302823 - SCURRY)Greenfield345 kV600 MW3.4 yrs58.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen