LAGOON CREEK is a substation-adjacent datacenter candidate site in Weakley County, Tennessee, interconnecting through MISO. It screens at 76.7/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationLAGOON CREEK
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW
LMP zoneMISO_ILLINOIS
Wholesale LMP$33.26/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth34
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPQuad State Internet PAH1 Colocation
IXP distance57.6 mi
Fiber providers3
Fiber coverage68.4%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance392.5 mi

Site characteristics

Parcel ownerTENNESSEE VALLEY AUTHORITY
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score62/100
Construction cost index49.3 (avg 100)

Location context

Nearest datacenterNewrays Two LLC Mining
DC distance28.9 mi
Nearest rail0.1 mi
Nearest gas pipeline6.6 mi
Nearest fiber route216.3 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.25¢/kWh
Industrial electricity6.79¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$4,680

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power15%
50
Fiber connectivity12%
67
Energy cost10%
88
Water risk8%
90
Natural hazard8%
62
Buildability7%
100
Labor market4%
50
DC cluster4%
60
Land / acreage3%
48
Construction cost3%
100
Gas pipeline2%
79
Tax incentive2%
100
Climate / cooling2%
45

Nearby comparable sites

Other scored datacenter candidate sites in Weakley County, ranked by DC Readiness.

Sites near LAGOON CREEK
SiteTypeVoltageCapacityQueue waitScore
GLEASONSubstation-Adjacent500 kV1,000 MW3.7 yrs76.0
Greenfield (JOHNSONVILLE - GLEASON)Greenfield500 kV1,000 MW3.7 yrs72.7
WEAKLEYSubstation-Adjacent500 kV1,000 MW3.7 yrs72.2
TAP152134Substation-Adjacent161 kV100 MW3.7 yrs70.8
Greenfield (WEAKLEY - GLEASON)Greenfield500 kV1,000 MW3.7 yrs68.9
MARTINSubstation-Adjacent161 kV100 MW3.7 yrs68.2
PIERCESubstation-Adjacent161 kV100 MW3.7 yrs64.3
Greenfield (WEAKLEY - LAGOON CREEK)Greenfield500 kV1,000 MW1.4 yrs63.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for LAGOON CREEK, Weakley County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.