Greenfield (OREBANK - NORTH BRISTOL)

Greenfield

Sullivan County, Tennessee · SERC

DC Readiness
61.3
Good / 100

Greenfield (OREBANK - NORTH BRISTOL) is a greenfield datacenter candidate site in Sullivan County, Tennessee, interconnecting through SERC. It screens at 61.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationOREBANK
Substation voltage138 kV
Available capacity100 MW
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.7 yrs
Recent queue wait3.5 yrs
Completion rate15%
Withdrawal rate85%

Connectivity

Nearest IXP801 Main Street - Lenoir
IXP distance61.0 mi
Fiber providers7
Fiber coverage79.3%
Nearest cloud providerAzure
Nearest cloud regioneastus
Cloud region distance146.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerKINGSPORT POWER CO
Land owner typeprivate
Buildability50.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score62/100
Construction cost index90.3 (avg 100)

Location context

Nearest datacenter801 Main Street - Lenoir
DC distance61.0 mi
Nearest rail5.2 mi
Nearest gas pipeline6.0 mi
Nearest fiber route165.1 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.51¢/kWh
Industrial electricity6.38¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$8,316

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
67
Fiber connectivity12%
69
Energy cost10%
90
Water risk8%
90
Natural hazard8%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
45
Land / acreage3%
57
Construction cost3%
75
Gas pipeline2%
81
Tax incentive2%
100
Climate / cooling2%
45

Nearby comparable sites

Other scored datacenter candidate sites in Sullivan County, ranked by DC Readiness.

Sites near Greenfield (OREBANK - NORTH BRISTOL)
SiteTypeVoltageCapacityQueue waitScore
BROADFORD (765 KV)Substation-Adjacent500 kV1,000 MW3.7 yrs77.9
SULLIVANSubstation-Adjacent500 kV1,000 MW3.7 yrs74.7
Greenfield (SULLIVAN - NAGEL)Greenfield500 kV1,000 MW3.7 yrs72.4
Greenfield (SULLIVAN - BROADFORD (765 KV))Greenfield500 kV1,000 MW3.7 yrs71.2
Greenfield (SULLIVAN - NAGEL)Greenfield500 kV1,000 MW3.7 yrs71.0
Greenfield (SULLIVAN - PHILLIPS BEND)Greenfield500 kV1,000 MW3.7 yrs70.7
NORTH JOHNSONSubstation-Adjacent161 kV100 MW3.7 yrs69.0
BLOUNTVILLE SW STATIONSubstation-Adjacent161 kV100 MW3.7 yrs68.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (OREBANK - NORTH BRISTOL), Sullivan County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.