Datacenter Sites in Edgefield, South Carolina
Edgefield has 21 scored datacenter candidate sites averaging 64.9/100 DC Readiness, with a catalogued aggregate of 2,100 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
21
Candidate sites
64.9/100
Avg DC Readiness
2,100 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Edgefield
Yessales_tax_exemption
Datacenter tax incentive
12.23¢/kWh
Commercial electricity
7.30¢/kWh
Industrial electricity
7
Fiber providers
Low
Water stress
$4,696
Land price / acre
2,000
Cooling degree days
2,400
Heating degree days
63°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment; fee-in-lieu of property tax for $50M+ investments.
By site type
Top datacenter sites in Edgefield
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN167525 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 63.8 |
| UNKNOWN116808 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 63.6 |
| TAP141824 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 63.4 |
| TAP141843 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 63.2 |
| UNKNOWN117193 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.9 |
| UNKNOWN116810 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.7 |
| UNKNOWN170038 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.6 |
| OZ Edgefield | Greenfield | — | — | 3.7 yrs | 62.0 |
| UNKNOWN116728 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 61.3 |
| UNKNOWN153960 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.9 |
| UNKNOWN116729 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.4 |
| TAP141834 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.0 |
| UNKNOWN116731 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.0 |
| UNKNOWN116976 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 59.8 |
| TAP141836 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 58.7 |
| Walter Farms Bird Seed Co. | Industrial | — | — | 1.0 yrs | 57.2 |
Edgefield datacenter FAQ
- How many datacenter sites are in Edgefield?
- 21 scored datacenter candidate sites, averaging 64.9/100 DC Readiness.
- Does Edgefield offer datacenter tax incentives?
- Sales tax exemption on DC equipment; fee-in-lieu of property tax for $50M+ investments.
- What is the natural-hazard risk in Edgefield?
- FEMA's National Risk Index rates Edgefield as "Relatively High" (score 40).
- What are industrial electricity rates in Edgefield?
- Average industrial electricity is 7.30¢/kWh and commercial is 12.23¢/kWh in Edgefield.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen