Greenfield (KAMMER (138KV) - WASHINGTON EN)

Greenfield

Monroe County, Ohio · PJM

DC Readiness
59.6
Good / 100

Greenfield (KAMMER (138KV) - WASHINGTON EN) is a greenfield datacenter candidate site in Monroe County, Ohio, interconnecting through PJM. It screens at 59.6/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationKAMMER (138KV)
Substation voltage345 kV
Available capacity600 MW
LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPCitynet Bridgeport
IXP distance56.0 mi
Fiber providers6
Fiber coverage55.1%
Nearest cloud providerGCP
Nearest cloud regionus-east5
Cloud region distance84.4 mi

Site characteristics

Site typeGreenfield
Parcel ownerAep Ohio Transmission Company,
Parcel APN290160160000
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index96.5 (avg 100)

Location context

Nearest datacenterCitynet Bridgeport
DC distance56.0 mi
Nearest rail11.7 mi
Nearest gas pipeline3.1 mi
Nearest fiber route54.6 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.94¢/kWh
Industrial electricity9.75¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$4,184

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
51
Fiber connectivity12%
21
Energy cost10%
91
Water risk8%
84
Natural hazard8%
70
Buildability7%
45
Labor market4%
50
DC cluster4%
50
Land / acreage3%
49
Construction cost3%
70
Gas pipeline2%
90
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Monroe County, ranked by DC Readiness.

Sites near Greenfield (KAMMER (138KV) - WASHINGTON EN)
SiteTypeVoltageCapacityQueue waitScore
KAMMER (138KV)Substation-Adjacent345 kV600 MW3.2 yrs69.9
UNKNOWN151772Substation-Adjacent138 kV100 MW3.2 yrs67.0
UNKNOWN116760Substation-Adjacent138 kV100 MW3.2 yrs66.9
Greenfield (KAMMER (138KV) - WASHINGTON EN)Greenfield345 kV600 MW3.2 yrs66.9
UNKNOWN116763Substation-Adjacent138 kV100 MW3.2 yrs66.7
TAP150325Substation-Adjacent138 kV100 MW3.2 yrs66.4
Greenfield (KAMMER (138KV) - WASHINGTON EN)Greenfield345 kV600 MW3.2 yrs65.8
Greenfield (KAMMER (138KV) - MUSKINGUM RIV)Greenfield345 kV600 MW3.2 yrs65.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (KAMMER (138KV) - WASHINGTON EN), Monroe County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.