Greenfield (FIRSTENERGY TORONTO - SOUTH AK)

Greenfield

Columbiana County, Ohio · PJM

DC Readiness
54.2
Fair / 100

Greenfield (FIRSTENERGY TORONTO - SOUTH AK) is a greenfield datacenter candidate site in Columbiana County, Ohio, interconnecting through PJM. It screens at 54.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationFIRSTENERGY TORONTO
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPLSTI 401 Market
IXP distance23.5 mi
Fiber providers6
Fiber coverage2.8%
Nearest cloud providerGCP
Nearest cloud regionus-east5
Cloud region distance53.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerBrogan Larry J Trustee
Parcel APN27-00112.000
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteUTICA EAST OHIO MIDSTREAM LLC KENSINGTON PROCESSING PLANT
Hazard sub-score60/100
Construction cost index80.4 (avg 100)

Location context

Nearest datacenterLSTI 401 Market
DC distance23.5 mi
Nearest rail0.3 mi
Nearest gas pipeline0.3 mi
Nearest fiber route74.7 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.16¢/kWh
Industrial electricity7.70¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$7,379

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
51
Fiber connectivity12%
13
Energy cost10%
91
Water risk8%
91
Natural hazard8%
60
Buildability7%
45
Labor market4%
50
DC cluster4%
70
Land / acreage3%
58
Construction cost3%
83
Gas pipeline2%
99
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Columbiana County, ranked by DC Readiness.

Sites near Greenfield (FIRSTENERGY TORONTO - SOUTH AK)
SiteTypeVoltageCapacityQueue waitScore
MANSFIELD STATIONSubstation-Adjacent345 kV600 MW3.2 yrs72.5
Greenfield (MANSFIELD STATION - HIGHLAND)Greenfield345 kV600 MW3.2 yrs69.1
Greenfield (MANSFIELD STATION - HANNA)Greenfield345 kV600 MW3.2 yrs67.7
Greenfield (FIRSTENERGY W H SAMMIS - TAP16)Greenfield345 kV600 MW3.2 yrs67.1
Greenfield (MANSFIELD STATION - HANNA)Greenfield345 kV600 MW3.2 yrs66.7
UNKNOWN113191Substation-Adjacent138 kV100 MW3.2 yrs66.7
Greenfield (MANSFIELD STATION - HANNA)Greenfield345 kV600 MW3.2 yrs66.6
Greenfield (BEAVER VALLEY - HANNA)Greenfield345 kV600 MW3.2 yrs66.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (FIRSTENERGY TORONTO - SOUTH AK), Columbiana County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.