Allegany County, New York · NYISO

DC Readiness
59.8
Good / 100

TAP140502 is a substation-adjacent datacenter candidate site in Allegany County, New York, interconnecting through NYISO. It screens at 59.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP140502
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneNYISO_WEST
Wholesale LMP$47.55/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionNYISO
Queue depth426
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate8%
Withdrawal rate92%

Connectivity

Nearest IXPVictory Technology Center
IXP distance43.8 mi
Fiber providers5
Fiber coverage64.9%
Nearest cloud providerGCP
Nearest cloud regionus-east5
Cloud region distance168.9 mi

Site characteristics

Parcel ownerROCHESTER GAS & ELECTRIC CORP
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index82.6 (avg 100)

Location context

Nearest datacenterVictory Technology Center
DC distance43.8 mi
Nearest rail9.5 mi
Nearest gas pipeline3.7 mi
Nearest fiber route113.6 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.31¢/kWh
Industrial electricity6.68¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$3,316

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
26
Fiber connectivity12%
62
Energy cost10%
70
Water risk8%
90
Natural hazard8%
65
Buildability7%
65
Labor market4%
50
DC cluster4%
45
Land / acreage3%
50
Construction cost3%
81
Gas pipeline2%
88
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Allegany County, ranked by DC Readiness.

Sites near TAP140502
SiteTypeVoltageCapacityQueue waitScore
Greenfield (HOMER CITY - FIVE MILE)Greenfield345 kV600 MW3.0 yrs63.9
UNKNOWN124588Substation-Adjacent115 kV100 MW3.0 yrs63.3
UNKNOWN124716Substation-Adjacent115 kV100 MW3.0 yrs63.2
TAP140650Substation-Adjacent115 kV100 MW3.0 yrs62.1
TAP140649Substation-Adjacent115 kV100 MW3.5 yrs61.1
Greenfield (UNKNOWN124581 - TAP140650)Greenfield115 kV100 MW3.0 yrs60.0
UNKNOWN124589Substation-Adjacent115 kV100 MW3.0 yrs59.7
Greenfield (UNKNOWN124587 - UNKNOWN124716)Greenfield115 kV100 MW3.0 yrs59.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.