Greenfield (CLARKSVILLE - PLEASANT VALLEY)

Greenfield

Mercer County, New Jersey · PJM

DC Readiness
63.3
Good / 100

Greenfield (CLARKSVILLE - PLEASANT VALLEY) is a greenfield datacenter candidate site in Mercer County, New Jersey, interconnecting through PJM. It screens at 63.3/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationCLARKSVILLE
Substation voltage230 kV
Available capacity300 MW
LMP zonePJM_PECO
Wholesale LMP$38.56/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth411
Avg queue wait3.0 yrs
Recent queue wait1.6 yrs
Completion rate19%
Withdrawal rate81%

Connectivity

Nearest IXPQTS Princeton (PJC1)
IXP distance18.6 mi
Fiber providers10
Fiber coverage97.6%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance164.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerPECO ENERGY CO
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score72/100
Construction cost index122.9 (avg 100)

Location context

Nearest datacenter501 West
DC distance11.8 mi
Nearest rail3.9 mi
Nearest gas pipeline3.0 mi
Nearest fiber route69.0 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.79¢/kWh
Industrial electricity7.15¢/kWh
Cooling degree days1,000
Heating degree days4,900
Land price / acre$26,811

Incentive detail: UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
42
Fiber connectivity12%
82
Energy cost10%
84
Water risk8%
84
Natural hazard8%
72
Buildability7%
45
Labor market4%
50
DC cluster4%
85
Land / acreage3%
30
Construction cost3%
48
Gas pipeline2%
90
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Mercer County, ranked by DC Readiness.

Sites near Greenfield (CLARKSVILLE - PLEASANT VALLEY)
SiteTypeVoltageCapacityQueue waitScore
EAST WINDSORSubstation-Adjacent500 kV1,000 MW2.6 yrs76.7
WINDSORSubstation-Adjacent230 kV300 MW2.6 yrs74.9
LAWRENCE SWSubstation-Adjacent230 kV300 MW3.0 yrs74.4
LAWRENCESubstation-Adjacent230 kV300 MW3.0 yrs74.1
KUSER ROADSubstation-Adjacent230 kV300 MW3.0 yrs73.3
CLARKSVILLESubstation-Adjacent230 kV300 MW3.0 yrs73.1
EMILIESubstation-Adjacent230 kV300 MW3.0 yrs72.7
WINDSORSubstation-Adjacent230 kV300 MW3.0 yrs71.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.