Broadwater County, Montana · SPP

DC Readiness
67.1
Good / 100

TAP205602 is a substation-adjacent datacenter candidate site in Broadwater County, Montana, interconnecting through SPP. It screens at 67.1/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP205602
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.08¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth1
Avg queue wait1.1 yrs
Recent queue wait0.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPMontana Opticom
IXP distance76.3 mi
Fiber providers3
Fiber coverage4.9%
Nearest cloud providerAzure
Nearest cloud regionwestus2
Cloud region distance378.2 mi

Site characteristics

Parcel ownerNorthwestern Corporation
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone D
Water stress (WRI)2.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score88/100
Construction cost index70.0 (avg 100)

Location context

Nearest datacenterDatacenter 758426349
DC distance71.5 mi
Nearest rail5.9 mi
Nearest gas pipeline8.5 mi
Nearest fiber route59.4 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Commercial electricity8.14¢/kWh
Industrial electricity5.64¢/kWh
Cooling degree days400
Heating degree days7,600
Land price / acre$1,894

Incentive detail: New/expanding industry tax abatement available for DC construction.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
74
Fiber connectivity12%
47
Energy cost10%
91
Water risk8%
56
Natural hazard8%
88
Buildability7%
80
Labor market4%
50
DC cluster4%
20
Land / acreage3%
61
Construction cost3%
92
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Broadwater County, ranked by DC Readiness.

Sites near TAP205602
SiteTypeVoltageCapacityQueue waitScore
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs70.5
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs70.0
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs69.4
Greenfield (THREE RIVERS - WILSALL)Greenfield230 kV300 MW1.1 yrs69.3
TOSTONSubstation-Adjacent138 kV100 MW1.1 yrs69.1
UNKNOWN204437Substation-Adjacent115 kV100 MW1.1 yrs69.1
THREE RIVERSSubstation-Adjacent230 kV300 MW1.1 yrs68.9
Greenfield (THREE RIVERS - WILSALL)Greenfield230 kV300 MW1.1 yrs68.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP205602, Broadwater County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.