Greenfield (UNKNOWN107928 - BROOKLINE)

Greenfield

Lawrence County, Missouri · ERCOT

DC Readiness
66.9
Good / 100

Greenfield (UNKNOWN107928 - BROOKLINE) is a greenfield datacenter candidate site in Lawrence County, Missouri, interconnecting through ERCOT. It screens at 66.9/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN107928
Substation voltage345 kV
Available capacity600 MW
LMP zoneERCOT_CENTRAL
Wholesale LMP$18.75/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPBluebird Underground Data Center
IXP distance25.4 mi
Fiber providers7
Fiber coverage45.0%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance308.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerENTERGY ARKANSAS INC
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score62/100
Construction cost index73.0 (avg 100)

Location context

Nearest datacenterBluebird Underground Data Center
DC distance25.4 mi
Nearest rail7.7 mi
Nearest gas pipeline8.1 mi
Nearest fiber route57.5 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.38¢/kWh
Industrial electricity8.90¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$4,465

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
55
Fiber connectivity12%
62
Energy cost10%
92
Water risk8%
87
Natural hazard8%
62
Buildability7%
75
Labor market4%
50
DC cluster4%
60
Land / acreage3%
48
Construction cost3%
89
Gas pipeline2%
74
Tax incentive2%
100
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Lawrence County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN107928 - BROOKLINE)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (UNKNOWN107928 - BROOKLINE)Greenfield345 kV600 MW3.4 yrs66.5
UNKNOWN117387Substation-Adjacent161 kV100 MW1.4 yrs66.5
Greenfield (UNKNOWN107928 - BROOKLINE)Greenfield345 kV600 MW3.4 yrs66.3
TAP153764Substation-Adjacent161 kV100 MW1.4 yrs66.1
UNKNOWN117430Substation-Adjacent161 kV100 MW1.4 yrs64.3
Greenfield (UNKNOWN107928 - BROOKLINE)Greenfield345 kV600 MW3.4 yrs64.1
EC FFE Lawrence CountyGreenfield1.4 yrs59.6
Greenfield (UNKNOWN117387 - TAP153764)Greenfield161 kV100 MW1.4 yrs59.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.