Greenfield (PLEASANT HILL - BENTON)

Greenfield

BENTON, Mississippi · MISO

DC Readiness
61.9
Good / 100

Greenfield (PLEASANT HILL - BENTON) is a greenfield datacenter candidate site in BENTON, Mississippi, interconnecting through MISO. It screens at 61.9/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationPLEASANT HILL
Substation voltage500 kV
Available capacity1,000 MW
LMP zoneMISO_MS
Wholesale LMP$31.68/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth13
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPExpedient Memphis
IXP distance39.3 mi
Fiber providers7
Fiber coverage52.7%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance460.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerBarber James E
Parcel APN1-0640-23-000-026.00
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteTORQUE CONVERTERS INC
Hazard sub-score45/100
Construction cost index80.5 (avg 100)

Location context

Nearest datacenterExpedient Memphis
DC distance39.3 mi
Nearest rail11.3 mi
Nearest gas pipeline2.3 mi
Nearest fiber route219.9 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.51¢/kWh
Industrial electricity7.59¢/kWh
Cooling degree days2,400
Heating degree days2,400
Land price / acre$2,707

Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
59
Fiber connectivity12%
20
Energy cost10%
85
Water risk8%
90
Natural hazard8%
45
Buildability7%
75
Labor market4%
50
DC cluster4%
40
Land / acreage3%
51
Construction cost3%
83
Gas pipeline2%
93
Tax incentive2%
100
Climate / cooling2%
5

Nearby comparable sites

Other scored datacenter candidate sites in BENTON, ranked by DC Readiness.

Sites near Greenfield (PLEASANT HILL - BENTON)
SiteTypeVoltageCapacityQueue waitScore
BENTONSubstation-Adjacent500 kV1,000 MW1.4 yrs74.8
Greenfield (CORDOVA - BENTON)Greenfield500 kV1,000 MW1.4 yrs67.8
Greenfield (CORDOVA - BENTON)Greenfield500 kV1,000 MW1.4 yrs65.4
Greenfield (PLEASANT HILL - BENTON)Greenfield500 kV1,000 MW1.4 yrs64.2
UNKNOWN169438Substation-Adjacent161 kV100 MW1.4 yrs62.8
TAP161194Substation-Adjacent161 kV100 MW1.4 yrs60.5
Greenfield (ASHLAND - TAP161194)Greenfield161 kV100 MW1.4 yrs60.2
Greenfield (TAP149909 - UNKNOWN169438)Greenfield161 kV100 MW1.4 yrs59.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.