UNKNOWN130320

Substation-Adjacent

Marshall County, Minnesota · SPP

DC Readiness
72.7
Excellent / 100

UNKNOWN130320 is a substation-adjacent datacenter candidate site in Marshall County, Minnesota, interconnecting through SPP. It screens at 72.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN130320
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth9
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXP232 20th St NW, East Grand Forks
IXP distance20.5 mi
Fiber providers4
Fiber coverage87.4%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance471.9 mi

Site characteristics

Parcel ownerSlaubaugh, Ronald W. & Dorothy A.
Parcel APN10347000
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteSRS ST BENEDICT CROOKSTON DENTAL
Hazard sub-score65/100
Construction cost index108.0 (avg 100)

Location context

Nearest datacenter232 20th St NW, East Grand Forks
DC distance20.5 mi
Nearest rail0.5 mi
Nearest gas pipeline1.6 mi
Nearest fiber route20.5 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.31¢/kWh
Industrial electricity5.40¢/kWh
Cooling degree days600
Heating degree days7,700
Land price / acre$3,168

Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
66
Fiber connectivity12%
82
Energy cost10%
92
Water risk8%
92
Natural hazard8%
65
Buildability7%
92
Labor market4%
50
DC cluster4%
60
Land / acreage3%
50
Construction cost3%
60
Gas pipeline2%
95
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Marshall County, ranked by DC Readiness.

Sites near UNKNOWN130320
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN130136Substation-Adjacent115 kV100 MW1.4 yrs68.5
Greenfield (UNKNOWN130322 - TAP133980)Greenfield115 kV100 MW1.4 yrs66.8
Greenfield (TAP133979 - TAP133980)Greenfield115 kV100 MW1.4 yrs65.5
Greenfield (UNKNOWN130322 - TAP133980)Greenfield115 kV100 MW1.4 yrs65.5
Greenfield (UNKNOWN130322 - TAP133980)Greenfield115 kV100 MW1.4 yrs65.1
Greenfield (UNKNOWN130181 - UNKNOWN134547)Greenfield115 kV100 MW1.4 yrs64.6
Greenfield (UNKNOWN130136 - TAP134503)Greenfield115 kV100 MW1.4 yrs62.0
Greenfield (UNKNOWN130136 - TAP134503)Greenfield115 kV100 MW1.4 yrs59.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.