EC Near Berlin

Greenfield

Worcester, Maryland · PJM

DC Readiness
52.5
Fair / 100

EC Near Berlin is a greenfield datacenter candidate site in Worcester, Maryland, interconnecting through PJM. It screens at 52.5/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_BGE
Wholesale LMP$49.41/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth304
Avg queue wait3.5 yrs
Recent queue wait3.2 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPAiNET MD-790R
IXP distance96.0 mi
Fiber providers7
Fiber coverage49.7%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance134.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerA Reggie Mariner Ii Irrevocable Tr
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands
Former usenear retired oil plant (5km)

Risk & environment

Flood zoneZone X
Water stress (WRI)0.80
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score68/100
Construction cost index103.5 (avg 100)

Location context

Nearest datacenterCyberNAP Glen Burnie
DC distance96.1 mi
Nearest rail3.3 mi
Nearest gas pipeline2.0 mi
Nearest fiber route2.7 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_credits)
Commercial electricity13.54¢/kWh
Industrial electricity11.29¢/kWh
Cooling degree days1,300
Heating degree days4,400
Land price / acre$8,232

Incentive detail: Enterprise Zone property tax credits; personal property tax credits on DC equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
42
Fiber connectivity12%
63
Energy cost10%
79
Water risk8%
86
Natural hazard8%
68
Buildability7%
15
Labor market4%
50
DC cluster4%
25
Land / acreage3%
50
Construction cost3%
64
Gas pipeline2%
94
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Worcester, ranked by DC Readiness.

Sites near EC Near Berlin
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN123255Substation-Adjacent138 kV100 MW3.5 yrs63.2
UNKNOWN123254Substation-Adjacent138 kV100 MW3.5 yrs63.1
UNKNOWN123257Substation-Adjacent138 kV100 MW3.5 yrs60.3
EC Near BerlinGreenfield3.5 yrs57.0
EC Near BerlinGreenfield3.5 yrs56.7
OZ WorcesterGreenfield3.5 yrs56.7
EC Near BerlinGreenfield3.5 yrs56.4
BerlinBrownfield18 MW3.5 yrs56.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Berlin, Worcester. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.