WILLIAM F WYMAN

Substation-Adjacent

Cumberland County, Maine · ISO-NE

DC Readiness
65.7
Good / 100

WILLIAM F WYMAN is a substation-adjacent datacenter candidate site in Cumberland County, Maine, interconnecting through ISO-NE. It screens at 65.7/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationWILLIAM F WYMAN
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
LMP zoneISONE_ME
Wholesale LMP$66.32/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionISO-NE
Queue depth45
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate25%
Withdrawal rate75%

Connectivity

Nearest IXPCENTRA PWM1 - Portland, Maine (340 Cumberland)
IXP distance8.5 mi
Fiber providers12
Fiber coverage58.4%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance499.5 mi

Site characteristics

Parcel ownerCENTRAL MAINE POWER CO
Land owner typeprivate
Buildability5.0/100
Land cover (NLCD)Water

Risk & environment

Flood zoneZone VE (SFHA)
Water stress (WRI)0.20
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score60/100
Construction cost index95.5 (avg 100)

Location context

Nearest datacenterFirstLight Data Center
DC distance8.5 mi
Nearest rail1.2 mi
Nearest gas pipeline6.2 mi
Nearest fiber route56.7 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity13.95¢/kWh
Industrial electricity12.34¢/kWh
Cooling degree days300
Heating degree days7,500
Land price / acre$9,968

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
44
Fiber connectivity12%
83
Energy cost10%
69
Water risk8%
95
Natural hazard8%
60
Buildability7%
5
Labor market4%
50
DC cluster4%
80
Land / acreage3%
39
Construction cost3%
70
Gas pipeline2%
80
Tax incentive2%
0
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Cumberland County, ranked by DC Readiness.

Sites near WILLIAM F WYMAN
SiteTypeVoltageCapacityQueue waitScore
BUXTONSubstation-Adjacent345 kV600 MW3.5 yrs74.8
RAVEN FARMSubstation-Adjacent345 kV600 MW3.5 yrs72.8
SURROWIECSubstation-Adjacent345 kV600 MW3.5 yrs72.7
BUXTONSubstation-Adjacent345 kV600 MW3.5 yrs71.6
SOUTH GORHAMSubstation-Adjacent345 kV600 MW3.5 yrs70.9
PRIDES CORNERSubstation-Adjacent115 kV100 MW3.5 yrs67.9
SEWALLSubstation-Adjacent115 kV100 MW3.5 yrs66.8
TAP136733Substation-Adjacent115 kV100 MW3.5 yrs66.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.