Greenfield (MONTGOMERY - PARADISE)

Greenfield

Todd County, Kentucky · PJM

DC Readiness
70.5
Excellent / 100

Greenfield (MONTGOMERY - PARADISE) is a greenfield datacenter candidate site in Todd County, Kentucky, interconnecting through PJM. It screens at 70.5/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationMONTGOMERY
Substation voltage500 kV
Available capacity1,000 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPRussellvile EPB Smartnet
IXP distance12.8 mi
Fiber providers4
Fiber coverage99.6%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance306.0 mi

Site characteristics

Site typeGreenfield
Parcel ownerTENNESSEE VALLEY AUTHORITY
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index84.6 (avg 100)

Location context

Nearest datacenterRussellvile EPB Smartnet
DC distance12.8 mi
Nearest rail8.9 mi
Nearest gas pipeline1.2 mi
Nearest fiber route164.6 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.85¢/kWh
Industrial electricity5.48¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$6,606

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
43
Fiber connectivity12%
76
Energy cost10%
85
Water risk8%
89
Natural hazard8%
70
Buildability7%
75
Labor market4%
50
DC cluster4%
80
Land / acreage3%
45
Construction cost3%
80
Gas pipeline2%
96
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Todd County, ranked by DC Readiness.

Sites near Greenfield (MONTGOMERY - PARADISE)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (MONTGOMERY - PARADISE)Greenfield500 kV1,000 MW4.6 yrs71.6
Greenfield (MONTGOMERY - PARADISE)Greenfield500 kV1,000 MW4.6 yrs69.9
Greenfield (MONTGOMERY - PARADISE)Greenfield500 kV1,000 MW4.6 yrs69.6
TAP155281Substation-Adjacent161 kV100 MW4.6 yrs66.7
Greenfield (MONTGOMERY - PARADISE)Greenfield500 kV1,000 MW4.6 yrs66.2
Greenfield (TAP155101 - TAP155281)Greenfield161 kV100 MW4.6 yrs64.7
Greenfield (TAP155101 - TAP155281)Greenfield161 kV100 MW4.6 yrs63.4
EC FFE Todd CountyGreenfield3.6 yrs61.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (MONTGOMERY - PARADISE), Todd County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.