Greenfield (TAP140094 - GHENT STATION)

Greenfield

Gallatin, Kentucky · PJM

DC Readiness
57.9
Good / 100

Greenfield (TAP140094 - GHENT STATION) is a greenfield datacenter candidate site in Gallatin, Kentucky, interconnecting through PJM. It screens at 57.9/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP140094
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPCyrusOne Florence
IXP distance27.6 mi
Fiber providers2
Fiber coverage81.0%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance137.0 mi

Site characteristics

Site typeGreenfield
Parcel ownerEAST KENTUCKY POWER COOP, INC
Land owner typeprivate
Buildability50.0/100
Land cover (NLCD)Mixed Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index65.0 (avg 100)

Location context

Nearest datacenterCyrusOne Florence
DC distance27.6 mi
Nearest rail1.4 mi
Nearest gas pipeline13.4 mi
Nearest fiber route36.9 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.15¢/kWh
Industrial electricity6.60¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$3,786

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
34
Fiber connectivity12%
73
Energy cost10%
83
Water risk8%
92
Natural hazard8%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
65
Land / acreage3%
49
Construction cost3%
96
Gas pipeline2%
57
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Gallatin, ranked by DC Readiness.

Sites near Greenfield (TAP140094 - GHENT STATION)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (CLIFTY CREEK - PIERCE)Greenfield345 kV600 MW3.0 yrs65.6
Greenfield (CLIFTY CREEK - PIERCE)Greenfield345 kV600 MW3.0 yrs65.0
Greenfield (GALLATIN - UNKNOWN130107)Greenfield138 kV100 MW3.0 yrs60.1
Greenfield (GALLATIN - UNKNOWN130107)Greenfield138 kV100 MW3.0 yrs59.1
Greenfield (GALLATIN - UNKNOWN130107)Greenfield138 kV100 MW3.0 yrs58.8
Warsaw Industrial ParkShovel-Ready52.1
Glencoe -- Site 077-019Shovel-Ready52.1
SpartaShovel-Ready51.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.