Greeley County, Kansas · SPP

DC Readiness
58.0
Good / 100

TAP155832 is a substation-adjacent datacenter candidate site in Greeley County, Kansas, interconnecting through SPP. It screens at 58.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP155832
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth16
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Fiber providers0
Fiber coverage0.0%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance372.5 mi

Site characteristics

Parcel ownerMIDWEST ENERGY INC
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)2.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index89.0 (avg 100)

Location context

Nearest datacenterCloud Storage Corp
DC distance137.3 mi
Nearest rail9.8 mi
Nearest gas pipeline9.1 mi
Nearest fiber route54.2 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity10.82¢/kWh
Industrial electricity9.28¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$1,795

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
51
Fiber connectivity12%
43
Energy cost10%
88
Water risk8%
52
Natural hazard8%
65
Buildability7%
65
Labor market4%
50
DC cluster4%
20
Land / acreage3%
53
Construction cost3%
76
Gas pipeline2%
71
Tax incentive2%
100
Climate / cooling2%
55

Nearby comparable sites

Other scored datacenter candidate sites in Greeley County, ranked by DC Readiness.

Sites near TAP155832
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN157111Substation-Adjacent115 kV100 MW3.5 yrs60.4
UNKNOWN119520Substation-Adjacent115 kV100 MW3.5 yrs60.0
TAP140577Substation-Adjacent115 kV100 MW3.5 yrs58.8
UNKNOWN119519Substation-Adjacent115 kV100 MW3.5 yrs58.8
OZ GreeleyGreenfield3.5 yrs55.5
Greenfield (UNKNOWN118142 - TAP140577)Greenfield115 kV100 MW3.5 yrs54.5
Greenfield (UNKNOWN119520 - TAP140579)Greenfield115 kV100 MW3.5 yrs53.1
Greenfield (UNKNOWN119521 - TAP155832)Greenfield115 kV100 MW3.5 yrs47.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP155832, Greeley County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.