Greenfield (WORTHINGTON PRIMARY SUBSTATION)

Greenfield

OWEN, Indiana · PJM

DC Readiness
67.4
Good / 100

Greenfield (WORTHINGTON PRIMARY SUBSTATION) is a greenfield datacenter candidate site in OWEN, Indiana, interconnecting through PJM. It screens at 67.4/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationWORTHINGTON PRIMARY SUBSTATION
Substation voltage345 kV
Available capacity600 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPIndiana University Data Center
IXP distance17.6 mi
Fiber providers4
Fiber coverage72.8%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance191.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerDUKE ENERGY INDIANA, LLC
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score68/100
Construction cost index64.0 (avg 100)

Location context

Nearest datacenterIU Data Center
DC distance17.6 mi
Nearest rail2.4 mi
Nearest gas pipeline4.7 mi
Nearest fiber route66.3 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.53¢/kWh
Industrial electricity9.47¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$5,396

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
35
Fiber connectivity12%
78
Energy cost10%
89
Water risk8%
90
Natural hazard8%
68
Buildability7%
80
Labor market4%
50
DC cluster4%
60
Land / acreage3%
47
Construction cost3%
97
Gas pipeline2%
85
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in OWEN, ranked by DC Readiness.

Sites near Greenfield (WORTHINGTON PRIMARY SUBSTATION)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (EDWARDSPORT STATION IGCC - AMO)Greenfield345 kV600 MW4.6 yrs68.7
Greenfield (THOMPSON - PETERSBURG STATION)Greenfield345 kV600 MW4.6 yrs68.5
Greenfield (THOMPSON - PETERSBURG STATION)Greenfield345 kV600 MW4.6 yrs67.6
Greenfield (THOMPSON - PETERSBURG STATION)Greenfield345 kV600 MW4.6 yrs67.3
Greenfield (UNKNOWN124767 - SPENCER)Greenfield230 kV300 MW4.6 yrs66.8
Greenfield (SPENCER - BLOOMINGTON (230KV))Greenfield230 kV300 MW3.0 yrs66.7
Greenfield (EDWARDSPORT STATION IGCC - AMO)Greenfield345 kV600 MW4.6 yrs66.7
Greenfield (EDWARDSPORT STATION IGCC - AMO)Greenfield345 kV600 MW4.6 yrs65.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.