EC Near Munster Landfill Gas-to-Energy

Greenfield

Lake, Indiana · PJM

DC Readiness
59.2
Good / 100

EC Near Munster Landfill Gas-to-Energy is a greenfield datacenter candidate site in Lake, Indiana, interconnecting through PJM. It screens at 59.2/100 DC Readiness and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.17¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPNETRIX - ALSIP
IXP distance20.8 mi
Fiber providers8
Fiber coverage60.7%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance27.4 mi

Site characteristics

Site typeGreenfield
Parcel ownerLake County Tr Co Tr 4412
Land owner typeprivate
Buildability50.0/100
Former usenear retired gas plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteMILESTONE CONTRACTORS L P
Hazard sub-score58/100
Construction cost index94.6 (avg 100)

Location context

Nearest datacenterDigital Crossroad
DC distance14.4 mi
Nearest rail1.5 mi
Nearest gas pipeline1.0 mi
Nearest fiber route32.1 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity16.78¢/kWh
Industrial electricity6.44¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$7,916

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
35
Fiber connectivity12%
75
Energy cost10%
84
Water risk8%
92
Natural hazard8%
58
Buildability7%
50
Labor market4%
50
DC cluster4%
95
Land / acreage3%
57
Construction cost3%
71
Gas pipeline2%
97
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Lake, ranked by DC Readiness.

Sites near EC Near Munster Landfill Gas-to-Energy
SiteTypeVoltageCapacityQueue waitScore
SHEFFIELDSubstation-Adjacent345 kV600 MW2.2 yrs76.9
BLUE ISLANDSubstation-Adjacent345 kV600 MW4.6 yrs75.9
SHEFFIELDSubstation-Adjacent345 kV600 MW4.6 yrs75.4
BURNHAMSubstation-Adjacent345 kV600 MW4.6 yrs75.1
UNKNOWN122743Substation-Adjacent345 kV600 MW4.6 yrs74.4
TAP138162Substation-Adjacent345 kV600 MW4.6 yrs74.4
MUNSTERSubstation-Adjacent345 kV600 MW4.6 yrs74.3
UNKNOWN121993Substation-Adjacent345 kV600 MW4.6 yrs74.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.