Greenfield (UNKNOWN122046 - ROODHOUSE WEST)

Greenfield

Greene County, Illinois · PJM

DC Readiness
56.7
Good / 100

Greenfield (UNKNOWN122046 - ROODHOUSE WEST) is a greenfield datacenter candidate site in Greene County, Illinois, interconnecting through PJM. It screens at 56.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN122046
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPTierPoint St. Louis – Millpark
IXP distance39.9 mi
Fiber providers2
Fiber coverage46.3%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance228.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerAMEREN ILLINOIS COMPANY
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index60.1 (avg 100)

Location context

Nearest datacenterTierPoint St. Louis – Millpark
DC distance39.9 mi
Nearest rail3.1 mi
Nearest gas pipeline0.7 mi
Nearest fiber route191.8 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.67¢/kWh
Industrial electricity3.10¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$7,667

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
44
Fiber connectivity12%
57
Energy cost10%
87
Water risk8%
88
Natural hazard8%
65
Buildability7%
45
Labor market4%
50
DC cluster4%
40
Land / acreage3%
43
Construction cost3%
100
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
70

Nearby comparable sites

Other scored datacenter candidate sites in Greene County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN122046 - ROODHOUSE WEST)
SiteTypeVoltageCapacityQueue waitScore
ROODHOUSE WESTSubstation-Adjacent138 kV100 MW4.6 yrs64.3
OZ GreeneGreenfield4.6 yrs60.0
EC FFE Greene CountyGreenfield4.6 yrs59.1
EC Coal Greene CountyGreenfield4.6 yrs56.8
Pearl StationBrownfield22 MW4.6 yrs55.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN122046 - ROODHOUSE WEST), Greene County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.