Datacenter Sites in Crisp, Georgia
Crisp has 14 scored datacenter candidate sites averaging 59.2/100 DC Readiness, with a catalogued aggregate of 2,100 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
14
Candidate sites
59.2/100
Avg DC Readiness
2,100 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Crisp
Yessales_tax_exemption
Datacenter tax incentive
14.42¢/kWh
Commercial electricity
8.57¢/kWh
Industrial electricity
5
Fiber providers
Low-Medium
Water stress
$3,063
Land price / acre
2,200
Cooling degree days
2,400
Heating degree days
64°F
Mean annual temp
Incentive detail: Sales tax exemption on data processing equipment; investment tax credits for $150M+ projects.
By site type
Top datacenter sites in Crisp
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN153048 | Substation-Adjacent | 115 kV | 100 MW | 5.8 yrs | 66.8 |
| UNKNOWN111854 | Substation-Adjacent | 115 kV | 100 MW | 5.8 yrs | 66.7 |
| UNKNOWN111852 | Substation-Adjacent | 115 kV | 100 MW | 5.8 yrs | 66.7 |
| TAP142445 | Substation-Adjacent | 115 kV | 100 MW | 5.8 yrs | 66.0 |
| Greenfield (FORTSON - NORTH TIFTON) | Greenfield | 500 kV | 1,000 MW | 3.7 yrs | 61.4 |
| UNKNOWN111853 | Substation-Adjacent | 115 kV | 100 MW | 5.8 yrs | 59.5 |
| Greenfield (UNKNOWN111743 - NORTH TIFTON) | Greenfield | 230 kV | 300 MW | 5.8 yrs | 58.9 |
| OZ Crisp | Greenfield | — | — | 5.8 yrs | 58.9 |
| OZ Crisp | Greenfield | — | — | 5.8 yrs | 58.6 |
| Greenfield (PITTS - TAP155968) | Greenfield | 115 kV | 100 MW | 5.8 yrs | 57.8 |
| CRISP PLANT | Substation-Adjacent | 115 kV | 100 MW | 5.8 yrs | 57.1 |
| OZ Crisp | Greenfield | — | — | 5.8 yrs | 56.5 |
| Greenfield (UNKNOWN111899 - TAP174817) | Greenfield | 115 kV | 100 MW | 5.8 yrs | 50.4 |
| Mine Site | Former Mine | — | — | — | 43.4 |
Crisp datacenter FAQ
- How many datacenter sites are in Crisp?
- 14 scored datacenter candidate sites, averaging 59.2/100 DC Readiness.
- Does Crisp offer datacenter tax incentives?
- Sales tax exemption on data processing equipment; investment tax credits for $150M+ projects.
- What is the natural-hazard risk in Crisp?
- FEMA's National Risk Index rates Crisp as "Relatively High" (score 40).
- What are industrial electricity rates in Crisp?
- Average industrial electricity is 8.57¢/kWh and commercial is 14.42¢/kWh in Crisp.
Dataset updated . Screening estimates derived from public data sources.