UNKNOWN111525

Substation-Adjacent

Cherokee County, Georgia · PJM

DC Readiness
68.0
Good / 100

UNKNOWN111525 is a substation-adjacent datacenter candidate site in Cherokee County, Georgia, interconnecting through PJM. It screens at 68.0/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 4.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN111525
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth177
Avg queue wait4.3 yrs
Recent queue wait4.3 yrs
Completion rate14%
Withdrawal rate86%

Connectivity

Nearest IXP365 Data Centers Alpharetta (GA1)
IXP distance3.5 mi
Fiber providers8
Fiber coverage74.6%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance255.8 mi

Site characteristics

Parcel ownerGEORGIA POWER CO
Land owner typeprivate
Buildability60.0/100

Risk & environment

Flood zoneZone AE (SFHA)
Water stress (WRI)1.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteAMAZON COM SERVICES LLC DTG2
Hazard sub-score35/100
Construction cost index100.2 (avg 100)

Location context

Nearest datacenterCox Data Center
DC distance2.4 mi
Nearest rail10.5 mi
Nearest gas pipeline9.5 mi
Nearest fiber route19.3 mi
County hazard (FEMA NRI)Relatively High (40)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.81¢/kWh
Industrial electricity7.48¢/kWh
Cooling degree days2,200
Heating degree days2,400
Land price / acre$9,874

Incentive detail: Sales tax exemption on data processing equipment; investment tax credits for $150M+ projects.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
35
Fiber connectivity12%
90
Energy cost10%
94
Water risk8%
86
Natural hazard8%
35
Buildability7%
60
Labor market4%
50
DC cluster4%
100
Land / acreage3%
47
Construction cost3%
67
Gas pipeline2%
69
Tax incentive2%
100
Climate / cooling2%
15

Nearby comparable sites

Other scored datacenter candidate sites in Cherokee County, ranked by DC Readiness.

Sites near UNKNOWN111525
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN111524Substation-Adjacent230 kV300 MW5.8 yrs76.1
UNKNOWN111160Substation-Adjacent230 kV300 MW5.8 yrs74.2
UNKNOWN110859Substation-Adjacent500 kV1,000 MW5.8 yrs73.7
UNKNOWN110862Substation-Adjacent230 kV300 MW5.8 yrs73.4
UNKNOWN111510Substation-Adjacent115 kV100 MW5.8 yrs70.6
UNKNOWN111133Substation-Adjacent115 kV100 MW5.8 yrs70.4
UNKNOWN111157Substation-Adjacent115 kV100 MW5.8 yrs70.2
Greenfield (UNKNOWN110634 - UNKNOWN110859)Greenfield500 kV1,000 MW5.8 yrs69.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN111525, Cherokee County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.