Garfield County, Colorado · WECC

DC Readiness
61.9
Good / 100

WHEELER is a substation-adjacent datacenter candidate site in Garfield County, Colorado, interconnecting through WECC. It screens at 61.9/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationWHEELER
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPSTRATA Vernal Data Center
IXP distance101.9 mi
Fiber providers6
Fiber coverage16.8%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance219.4 mi

Site characteristics

Parcel ownerSolvay Chemicals, Inc
Parcel APN240902200148
Land owner typeprivate
Buildability60.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)3.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteAMERICAN SODA LLC SOLVAY CHEMICALS
Hazard sub-score65/100
Construction cost index91.5 (avg 100)

Location context

Nearest datacenterStrata Networks
DC distance101.9 mi
Nearest rail0.3 mi
Nearest gas pipeline7.1 mi
Nearest fiber route100.2 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.39¢/kWh
Industrial electricity9.05¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$3,654

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
33
Fiber connectivity12%
55
Energy cost10%
89
Water risk8%
56
Natural hazard8%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
50
Construction cost3%
74
Gas pipeline2%
77
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Garfield County, ranked by DC Readiness.

Sites near WHEELER
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN203894Substation-Adjacent230 kV300 MW1.7 yrs66.7
TAP203975Substation-Adjacent345 kV600 MW1.7 yrs64.4
RIFLE UTESubstation-Adjacent345 kV600 MW1.7 yrs64.0
STARKEY GULCHSubstation-Adjacent230 kV300 MW1.7 yrs64.0
PARACHUTESubstation-Adjacent230 kV300 MW1.7 yrs62.9
MIDDLE FORKSubstation-Adjacent230 kV300 MW1.7 yrs62.5
Greenfield (CRAIG - TAP203975)Greenfield345 kV600 MW1.7 yrs59.7
Greenfield (RIFLE UTE - GRAND JUNCTION)Greenfield345 kV600 MW1.7 yrs58.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WHEELER, Garfield County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.