UNKNOWN201402

Substation-Adjacent

Clear Creek County, Colorado · WECC

DC Readiness
60.2
Good / 100

UNKNOWN201402 is a substation-adjacent datacenter candidate site in Clear Creek County, Colorado, interconnecting through WECC. It screens at 60.2/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN201402
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPColoradoColo - Lakewood (LKWD)
IXP distance31.6 mi
Fiber providers3
Fiber coverage9.3%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance335.0 mi

Site characteristics

Parcel ownerUs Forest Service
Parcel APN195927100901
Land owner typeprivate
Buildability85.0/100
Land cover (NLCD)Barren Land

Risk & environment

Flood zoneZone X
Water stress (WRI)3.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index72.8 (avg 100)

Location context

Nearest datacenterColoradoColo - Lakewood (LKWD)
DC distance31.6 mi
Nearest rail3.1 mi
Nearest gas pipeline7.3 mi
Nearest fiber route44.6 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.15¢/kWh
Industrial electricity8.50¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$3,896

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
33
Fiber connectivity12%
7
Energy cost10%
89
Water risk8%
59
Natural hazard8%
75
Buildability7%
85
Labor market4%
50
DC cluster4%
40
Land / acreage3%
49
Construction cost3%
89
Gas pipeline2%
77
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Clear Creek County, ranked by DC Readiness.

Sites near UNKNOWN201402
SiteTypeVoltageCapacityQueue waitScore
HENDERSONSubstation-Adjacent115 kV100 MW1.7 yrs59.0
UNKNOWN201514Substation-Adjacent115 kV100 MW1.7 yrs58.5
Greenfield (DILLION - UNKNOWN201402)Greenfield230 kV300 MW1.7 yrs55.1
Greenfield (UNKNOWN201402 - IDAHO SPRINGS)Greenfield230 kV300 MW1.7 yrs54.9
Greenfield (HENDERSON - PORTAL)Greenfield115 kV100 MW1.7 yrs52.1
OZ Clear CreekGreenfield1.7 yrs50.2
Greenfield (DILLION - UNKNOWN201402)Greenfield230 kV300 MW1.7 yrs49.7
Greenfield (UNKNOWN201514 - HENDERSON)Greenfield115 kV100 MW1.7 yrs49.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN201402, Clear Creek County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.