TIETON DAM HYDRO ELECTRIC PROJECT

Substation

Washington · PACIFICORP

Max voltage
115
kV

TIETON DAM HYDRO ELECTRIC PROJECT is an electric transmission substation in Washington, operated by PACIFICORP. It is classified as sub-transmission (115 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines1

Ownership & operation

OperatorPACIFICORP
Coordinates46.6581, -121.1285

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#73060115 kVPACIFICORP0.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TIETON DAM HYDRO ELECTRIC PROJECT, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TIETON DAM HYDRO ELECTRIC PROJECT substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN201516Substation-AdjacentWAYakima County115 kV100 MW1.7 yrs66.2
HAUSEN CREEKSubstation-AdjacentWAYakima County115 kV100 MW1.7 yrs63.1
UNKNOWN201256Substation-AdjacentWAYakima County115 kV100 MW1.7 yrs59.2
Greenfield (HAUSEN CREEK - HAUSEN CREEK)GreenfieldWAYakima County115 kV100 MW1.7 yrs58.6
Greenfield (UNKNOWN201516 - UNKNOWN201256)GreenfieldWAYakima County115 kV100 MW1.7 yrs58.5
UNKNOWN206491Substation-AdjacentWAYakima County115 kV100 MW1.7 yrs58.0
Greenfield (UNKNOWN201516 - UNKNOWN201256)GreenfieldWAYakima County115 kV100 MW1.7 yrs56.8
Greenfield (HAUSEN CREEK - HAUSEN CREEK)GreenfieldWAYakima County115 kV100 MW1.7 yrs54.5

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen