TAP209286

Substation

Washington · PUD NO 1 OF CHELAN COUNTY

Max voltage
115
kV

TAP209286 is an electric transmission substation in Washington, operated by PUD NO 1 OF CHELAN COUNTY. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorPUD NO 1 OF CHELAN COUNTY
Coordinates47.7709, -120.9971

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#77965115 kVPUD NO 1 OF CHELAN COUNTY13.2 mi
#77968115 kVPUD NO 1 OF CHELAN COUNTY0.0 mi
#77969115 kVPUD NO 1 OF CHELAN COUNTY6.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP209286, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP209286 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN203124Substation-AdjacentWAChelan County115 kV100 MW1.7 yrs65.4
Greenfield (CHIEF JOSEPH - MONROE)GreenfieldWAChelan County500 kV1,000 MW1.7 yrs65.2
ANDERSON CANYONSubstation-AdjacentWAChelan County115 kV100 MW1.7 yrs64.5
UNKNOWN202969Substation-AdjacentWAChelan County115 kV100 MW1.7 yrs64.2
Greenfield (CHIEF JOSEPH - MONROE)GreenfieldWAChelan County500 kV1,000 MW1.7 yrs63.2
TAP209283Substation-AdjacentWAChelan County115 kV100 MW1.7 yrs62.6
HYAKSubstation-AdjacentWAKing County138 kV100 MW1.7 yrs62.6
UNKNOWN202968Substation-AdjacentWAChelan County115 kV100 MW1.7 yrs62.4

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP209286 substation, Washington. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.