TAP209273

Substation

Washington · PUD NO 1 OF OKANOGAN COUNTY

Max voltage
115
kV

TAP209273 is an electric transmission substation in Washington, operated by PUD NO 1 OF OKANOGAN COUNTY. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorPUD NO 1 OF OKANOGAN COUNTY
Coordinates48.1024, -119.7969

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#77937115 kVPUD NO 1 OF OKANOGAN COUNTY7.7 mi
#77938115 kVPUD NO 1 OF OKANOGAN COUNTY0.4 mi
#77939115 kVPUD NO 1 OF OKANOGAN COUNTY0.4 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP209273, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP209273 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
CHIEF JOSEPHSubstation-AdjacentWADouglas County500 kV1,000 MW1.7 yrs67.7
UNKNOWN206474Substation-AdjacentWAOkanogan County275 kV300 MW1.7 yrs66.7
FOSTER CREEKSubstation-AdjacentWADouglas County230 kV300 MW1.7 yrs66.0
EAST OMAKSubstation-AdjacentWAOkanogan County230 kV300 MW1.7 yrs65.8
WELLSSubstation-AdjacentWADouglas County230 kV300 MW1.7 yrs65.6
Greenfield (CHIEF JOSEPH - MONROE)GreenfieldWADouglas County500 kV1,000 MW1.7 yrs65.3
Greenfield (CHIEF JOSEPH - MONROE)GreenfieldWADouglas County500 kV1,000 MW1.7 yrs64.8
TAP206318Substation-AdjacentWADouglas County115 kV100 MW1.7 yrs64.4

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP209273 substation, Washington. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.