TAP207876

Substation

Washington · PUD 1 OF SNOHOMISH COUNTY

Max voltage
115
kV

TAP207876 is an electric transmission substation in Washington, operated by PUD 1 OF SNOHOMISH COUNTY. It is classified as sub-transmission (115 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines2

Ownership & operation

OperatorPUD 1 OF SNOHOMISH COUNTY
Co-ownerPUGET SOUND ENERGY INC
Coordinates48.1665, -122.2192

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#78618115 kVPUGET SOUND ENERGY INC3.1 mi
#78619115 kVPUD 1 OF SNOHOMISH COUNTY4.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP207876, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP207876 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
SNO-KINGSubstation-AdjacentWAKitsap County500 kV1,000 MW1.7 yrs77.1
MONROESubstation-AdjacentWASnohomish County500 kV1,000 MW1.7 yrs76.2
SNOHOMISHSubstation-AdjacentWASnohomish County345 kV600 MW1.7 yrs75.2
TAP200917Substation-AdjacentWASnohomish County500 kV1,000 MW1.7 yrs74.7
BOTHELLSubstation-AdjacentWASnohomish County230 kV300 MW1.7 yrs73.9
TAP206030Substation-AdjacentWASnohomish County230 kV300 MW1.7 yrs72.7
MURRAYSubstation-AdjacentWASnohomish County230 kV300 MW1.7 yrs72.1
Greenfield (TAP200917 - SNO-KING)GreenfieldWASnohomish County500 kV1,000 MW1.7 yrs71.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP207876 substation, Washington. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.