TAP206318

Substation

Washington · PUD NO 1 OF CHELAN COUNTY

Max voltage
115
kV

TAP206318 is an electric transmission substation in Washington, operated by PUD NO 1 OF CHELAN COUNTY. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorPUD NO 1 OF CHELAN COUNTY
Coordinates47.7775, -120.1389

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#72623115 kVPUD NO 1 OF CHELAN COUNTY8.2 mi
#77875115 kVPUD NO 1 OF CHELAN COUNTY7.6 mi
#77876115 kVPUD NO 1 OF CHELAN COUNTY3.9 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP206318, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP206318 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
SICKLERSubstation-AdjacentWAChelan County500 kV1,000 MW1.7 yrs70.7
ROCKY REACHSubstation-AdjacentWAChelan County345 kV600 MW1.7 yrs68.9
Greenfield (SCHULTZ - SICKLER)GreenfieldWADouglas County500 kV1,000 MW1.7 yrs68.6
EASTMONTSubstation-AdjacentWAKittitas County115 kV100 MW1.7 yrs68.0
TAP209238Substation-AdjacentWAChelan County115 kV100 MW1.7 yrs67.8
Greenfield (GRAND COULEE 500KV - COLUMBIA)GreenfieldWAGrant County500 kV1,000 MW1.7 yrs67.7
Greenfield (CHIEF JOSEPH - MONROE)GreenfieldWAChelan County500 kV1,000 MW1.7 yrs67.3
Greenfield (CHIEF JOSEPH - MONROE)GreenfieldWAChelan County500 kV1,000 MW1.7 yrs67.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.