TAP206033

Substation

Washington · PUD NO 1 OF KITTITAS COUNTY

Max voltage
230
kV

TAP206033 is an electric transmission substation in Washington, operated by PUD NO 1 OF KITTITAS COUNTY. It is classified as high-voltage (230 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage230 kV
Voltage classHigh-voltage (230 kV)
Connected lines3

Ownership & operation

OperatorPUD NO 1 OF KITTITAS COUNTY
Co-ownerPUD NO 2 OF GRANT COUNTY
Coordinates46.6943, -119.9023

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#74110230 kVPUD NO 1 OF KITTITAS COUNTY13.5 mi
#74111230 kVPUD NO 1 OF KITTITAS COUNTY0.0 mi
#74121230 kVPUD NO 2 OF GRANT COUNTY3.8 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP206033, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP206033 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
HANFORDSubstation-AdjacentWABenton County500 kV1,000 MW1.7 yrs71.4
OUTLOOKSubstation-AdjacentWABenton County230 kV300 MW1.7 yrs70.5
WAUTOMASubstation-AdjacentWABenton County500 kV1,000 MW1.7 yrs70.2
VANTAGESubstation-AdjacentWAGrant County500 kV1,000 MW1.7 yrs69.6
WANAPUMSubstation-AdjacentWAGrant County230 kV300 MW1.7 yrs69.0
UNKNOWN206036Substation-AdjacentWAGrant County230 kV300 MW1.7 yrs68.4
WIND RIDGESubstation-AdjacentWAKittitas County230 kV300 MW1.7 yrs68.2
ALFALFASubstation-AdjacentWAYakima County230 kV300 MW1.7 yrs68.0

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP206033 substation, Washington. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.