TAP203487 is an electric transmission substation in Washington, operated by BONNEVILLE POWER ADMINISTRATION. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorBONNEVILLE POWER ADMINISTRATION
Coordinates47.8385, -117.4104

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#68206115 kVBONNEVILLE POWER ADMINISTRATION0.0 mi
#68207115 kVBONNEVILLE POWER ADMINISTRATION1.7 mi
#79028115 kVBONNEVILLE POWER ADMINISTRATION0.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP203487, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP203487 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
WESTSIDESubstation-AdjacentWASpokane County230 kV300 MW1.7 yrs73.4
UPRIVER DAM HYDRO PLANTSubstation-AdjacentWASpokane County230 kV300 MW1.7 yrs71.8
TAP205408Substation-AdjacentIDKootenai County138 kV100 MW1.7 yrs71.2
BELLSubstation-AdjacentWASpokane County500 kV1,000 MW1.7 yrs70.8
LANCASTERSubstation-AdjacentWASpokane County230 kV300 MW1.7 yrs70.8
UNKNOWN201468Substation-AdjacentWASpokane County230 kV300 MW1.7 yrs70.3
OTIS ORCHARDSSubstation-AdjacentWASpokane County115 kV100 MW1.7 yrs69.9
COLLEGE AND WALNUTSubstation-AdjacentWASpokane County115 kV100 MW1.7 yrs69.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP203487 substation, Washington. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.