TEMPLE PECAN CREEK is an electric transmission substation in Texas, operated by ONCOR ELECTRIC DELIVERY CO.. It is classified as high-voltage (345 kv) and connects 5 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage138 kV
Voltage classHigh-voltage (345 kV)
Connected lines5

Ownership & operation

OperatorONCOR ELECTRIC DELIVERY CO.
StateTexas
Coordinates31.1296, -97.2611

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#88414345 kVONCOR ELECTRIC DELIVERY CO.IN SERVICE28.6 mi
#92006345 kVONCOR ELECTRIC DELIVERY CO.IN SERVICE28.6 mi
#80948138 kVONCOR ELECTRIC DELIVERY CO.5.0 mi
#85635138 kVONCOR ELECTRIC DELIVERY CO.IN SERVICE4.5 mi
#88204138 kVONCOR ELECTRIC DELIVERY CO.IN SERVICE4.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TEMPLE PECAN CREEK, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TEMPLE PECAN CREEK substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
Lake CreekBrownfieldTXMcLennan1,357 MW73.1
LAKE CREEKSubstation-AdjacentTXMcLennan County345 kV600 MW3.4 yrs72.8
UNKNOWN306704Substation-AdjacentTXMcLennan County345 kV600 MW3.4 yrs70.7
TEMPLE PECAN CREEKSubstation-AdjacentTXBell County345 kV600 MW3.4 yrs70.2
UNKNOWN301533Substation-AdjacentTXBell County345 kV600 MW3.4 yrs69.2
UNKNOWN309681Substation-AdjacentTXMcLennan County138 kV100 MW3.4 yrs68.5
TAP312626Substation-AdjacentTXMcLennan County138 kV100 MW3.4 yrs68.0
UNKNOWN307653Substation-AdjacentTXBell County345 kV600 MW3.4 yrs67.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TEMPLE PECAN CREEK substation, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.