TAP307924

Substation

Texas · AEP TEXAS CENTRAL CO.

Max voltage
138
kV

TAP307924 is an electric transmission substation in Texas, operated by AEP TEXAS CENTRAL CO.. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorAEP TEXAS CENTRAL CO.
Co-ownerAEP TEXAS CENTRAL COMPANY
StateTexas
Coordinates28.8759, -96.1072

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#85804138 kVAEP TEXAS CENTRAL CO.IN SERVICE5.9 mi
#86896138 kVAEP TEXAS CENTRAL COMPANYIN SERVICE6.5 mi
#91505138 kVAEP TEXAS CENTRAL CO.IN SERVICE5.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP307924, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP307924 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
SOUTH TEXAS PROJECTSubstation-AdjacentTXMatagorda County345 kV600 MW3.4 yrs66.8
BLESSINGSubstation-AdjacentTXMatagorda County345 kV600 MW3.4 yrs65.0
UNKNOWN310390Substation-AdjacentTXBrazoria County138 kV100 MW3.4 yrs64.1
UNKNOWN302074Substation-AdjacentTXMatagorda County138 kV100 MW3.4 yrs63.1
UNKNOWN304209Substation-AdjacentTXWharton County138 kV100 MW3.4 yrs63.1
PLEDGERSubstation-AdjacentTXWharton County138 kV100 MW3.4 yrs63.0
NEW GULFSubstation-AdjacentTXWharton County138 kV100 MW3.4 yrs63.0
UNKNOWN306764Substation-AdjacentTXFort Bend County138 kV100 MW3.4 yrs63.0

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen