TAP302562

Substation

Texas · JASPER-NEWTON ELEC COOP, INC

Max voltage
138
kV

TAP302562 is an electric transmission substation in Texas, operated by JASPER-NEWTON ELEC COOP, INC. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorJASPER-NEWTON ELEC COOP, INC
StateTexas
Coordinates30.6984, -93.7982

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#80020138 kVJASPER-NEWTON ELEC COOP, INCIN SERVICE29.4 mi
#80639138 kVIN SERVICE6.7 mi
#92246138 kVJASPER-NEWTON ELEC COOP, INCIN SERVICE6.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP302562, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP302562 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
SAM DAMSubstation-AdjacentTXJasper County138 kV100 MW3.4 yrs63.2
Greenfield (HARTBURG - LEACH)GreenfieldTXNewton County500 kV1,000 MW3.4 yrs62.8
UNKNOWN302189Substation-AdjacentTXSabine County138 kV100 MW3.4 yrs62.4
UNKNOWN304495Substation-AdjacentTXOrange County138 kV100 MW3.4 yrs62.3
UNKNOWN305966Substation-AdjacentTXTyler County138 kV100 MW3.4 yrs62.3
Greenfield (HARTBURG - LEACH)GreenfieldTXNewton County500 kV1,000 MW3.4 yrs62.2
UNKNOWN307120Substation-AdjacentTXJasper County138 kV100 MW3.4 yrs62.2
UNKNOWN304419Substation-AdjacentTXJasper County138 kV100 MW3.4 yrs62.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP302562 substation, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.