TAP148980 is an electric transmission substation in Texas, operated by PUBLIC SERVICE CO OF OKLAHOMA. It is classified as sub-transmission (138 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines3

Ownership & operation

OperatorPUBLIC SERVICE CO OF OKLAHOMA
StateTexas
Coordinates34.0272, -95.1990

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#3198138 kVPUBLIC SERVICE CO OF OKLAHOMAIN SERVICE16.8 mi
#34209138 kVPUBLIC SERVICE CO OF OKLAHOMAIN SERVICE10.8 mi
#44011138 kVPUBLIC SERVICE CO OF OKLAHOMAIN SERVICE0.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP148980, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP148980 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
HUGO (345 KV)Substation-AdjacentOKChoctaw County345 kV600 MW3.4 yrs69.6
UNKNOWN300188Substation-AdjacentTXLamar County345 kV600 MW3.4 yrs67.2
UNKNOWN118754Substation-AdjacentOKMcCurtain County138 kV100 MW3.4 yrs66.4
Greenfield (HUGO (345 KV) - VALLIANT)GreenfieldOKMcCurtain County345 kV600 MW3.4 yrs65.8
TAP142404Substation-AdjacentOKMcCurtain County138 kV100 MW3.4 yrs65.7
UNKNOWN118751Substation-AdjacentOKMcCurtain County138 kV100 MW3.4 yrs65.4
VALLIANTSubstation-AdjacentTXRed River County345 kV600 MW3.4 yrs65.2
Greenfield (HUGO (345 KV) - SUNNYSIDE)GreenfieldOKChoctaw County345 kV600 MW3.4 yrs64.8

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP148980 substation, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.