PERMIAN BASIN 345
SubstationTexas · ONCOR ELECTRIC DELIVERY CO.
PERMIAN BASIN 345 is an electric transmission substation in Texas, operated by ONCOR ELECTRIC DELIVERY CO.. It is classified as sub-transmission (138 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #80972 | 138 kV | ONCOR ELECTRIC DELIVERY CO. | UNDER CONSTRUCTION | 0.6 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of PERMIAN BASIN 345, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| PERMIAN BASIN SWITCHING STATION | Substation-Adjacent | TX | Ward County | 138 kV | 100 MW | 3.4 yrs | 62.9 |
| WARD GULF | Substation-Adjacent | TX | Ward County | 138 kV | 100 MW | 3.4 yrs | 62.1 |
| WICKETT GULF | Substation-Adjacent | TX | Ward County | 138 kV | 100 MW | 3.4 yrs | 61.7 |
| UNKNOWN300550 | Substation-Adjacent | TX | Ector County | 138 kV | 100 MW | 3.4 yrs | 61.7 |
| MIDWAY | Substation-Adjacent | TX | Winkler County | 138 kV | 100 MW | 3.4 yrs | 61.7 |
| CHEYENE | Substation-Adjacent | TX | Winkler County | 138 kV | 100 MW | 3.4 yrs | 61.6 |
| TAP310909 | Substation-Adjacent | TX | Winkler County | 138 kV | 100 MW | 3.4 yrs | 60.9 |
| TAP315848 | Substation-Adjacent | TX | Loving County | 138 kV | 100 MW | 3.4 yrs | 60.7 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for PERMIAN BASIN 345 substation, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.