GRIMES

Substation

Texas · ENTERGY TEXAS INC.

Max voltage
345
kV

GRIMES is an electric transmission substation in Texas, operated by ENTERGY TEXAS INC.. It is classified as high-voltage (345 kv) and connects 6 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage138 kV
Voltage classHigh-voltage (345 kV)
Connected lines6

Ownership & operation

OperatorENTERGY TEXAS INC.
Co-ownerMID-SOUTH ELECTRIC COOP ASSN
StateTexas
Coordinates30.6239, -95.9094

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#82928345 kVENTERGY TEXAS INC.IN SERVICE64.0 mi
#87348345 kVMID-SOUTH ELECTRIC COOP ASSNIN SERVICE2.6 mi
#80037138 kVIN SERVICE24.3 mi
#85605138 kVMID-SOUTH ELECTRIC COOP ASSNIN SERVICE14.5 mi
#86778138 kVMID-SOUTH ELECTRIC COOP ASSNIN SERVICE26.2 mi
#92687138 kVMID-SOUTH ELECTRIC COOP ASSN24.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of GRIMES, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near GRIMES substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
JACK CREEKSubstation-AdjacentTXBrazos County345 kV600 MW3.4 yrs72.6
SINGLETONSubstation-AdjacentTXGrimes County345 kV600 MW3.4 yrs71.9
UNKNOWN302822Substation-AdjacentTXMontgomery County230 kV300 MW3.4 yrs71.8
GIBBONS CREEKSubstation-AdjacentTXGrimes County345 kV600 MW3.4 yrs69.4
TAP312651Substation-AdjacentTXBrazos County138 kV100 MW3.4 yrs69.1
GRIMESSubstation-AdjacentTXGrimes County345 kV600 MW3.4 yrs68.6
WALDENSubstation-AdjacentTXMontgomery County138 kV100 MW3.4 yrs68.4
TAP312647Substation-AdjacentTXBrazos County138 kV100 MW3.4 yrs68.4

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for GRIMES substation, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.