BIG FOOT

Substation

Texas · AEP TEXAS CENTRAL COMPANY

Max voltage
345
kV

BIG FOOT is an electric transmission substation in Texas, operated by AEP TEXAS CENTRAL COMPANY. It is classified as high-voltage (345 kv) and connects 5 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage138 kV
Voltage classHigh-voltage (345 kV)
Connected lines5

Ownership & operation

OperatorAEP TEXAS CENTRAL COMPANY
StateTexas
Coordinates29.0309, -98.9328

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#86444345 kVAEP TEXAS CENTRAL COMPANYIN SERVICE6.1 mi
#92630345 kVAEP TEXAS CENTRAL COMPANYIN SERVICE29.9 mi
#88861138 kVAEP TEXAS CENTRAL COMPANYIN SERVICE14.8 mi
#89032138 kVAEP TEXAS CENTRAL COMPANYIN SERVICE6.2 mi
#89718138 kVAEP TEXAS CENTRAL COMPANYIN SERVICE14.8 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of BIG FOOT, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near BIG FOOT substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
CAGNON ROADSubstation-AdjacentTXBexar County345 kV600 MW3.4 yrs74.8
LEON CREEKSubstation-AdjacentTXBexar County345 kV600 MW3.4 yrs71.7
Leon CreekBrownfieldTXBexar189 MW71.4
MERIDA STREETSubstation-AdjacentTXBexar County138 kV100 MW3.4 yrs69.1
SOUTH SAN ANTONIOSubstation-AdjacentTXBexar County138 kV100 MW3.4 yrs69.0
PALO ALTOSubstation-AdjacentTXBexar County138 kV100 MW3.4 yrs68.9
MEDINA BASESubstation-AdjacentTXBexar County138 kV100 MW3.4 yrs68.8
HOWARDSubstation-AdjacentTXBexar County138 kV100 MW3.4 yrs68.8

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen