HILL

Substation

Tennessee · APPALACHIAN POWER CO

Max voltage
138
kV

HILL is an electric transmission substation in Tennessee, operated by APPALACHIAN POWER CO. It is classified as sub-transmission (138 kv) and connects 1 transmission line. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines1

Ownership & operation

OperatorAPPALACHIAN POWER CO
Coordinates36.7224, -82.6348

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#37088138 kVAPPALACHIAN POWER COIN SERVICE12.9 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of HILL, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near HILL substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
NAGELSubstation-AdjacentVAScott County500 kV1,000 MW3.7 yrs78.2
BROADFORD (765 KV)Substation-AdjacentTNSullivan County500 kV1,000 MW3.7 yrs77.9
PHILLIPS BENDSubstation-AdjacentTNHawkins County500 kV1,000 MW3.7 yrs77.2
SULLIVANSubstation-AdjacentTNSullivan County500 kV1,000 MW3.7 yrs74.7
Greenfield (PHILLIPS BEND - NAGEL)GreenfieldVAScott County500 kV1,000 MW3.7 yrs73.9
Greenfield (SULLIVAN - NAGEL)GreenfieldTNHawkins County500 kV1,000 MW3.7 yrs73.1
Greenfield (SULLIVAN - NAGEL)GreenfieldTNSullivan County500 kV1,000 MW3.7 yrs72.4
HILLSubstation-AdjacentVAScott County138 kV100 MW3.7 yrs71.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for HILL substation, Tennessee. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.