EDENS RIDGE

Substation

Tennessee · KINGSPORT POWER CO

Max voltage
138
kV

EDENS RIDGE is an electric transmission substation in Tennessee, operated by KINGSPORT POWER CO. It is classified as sub-transmission (138 kv) and connects 6 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines6

Ownership & operation

OperatorKINGSPORT POWER CO
Coordinates36.5106, -82.5387

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#5438138 kVKINGSPORT POWER COIN SERVICE5.0 mi
#5763138 kVKINGSPORT POWER COIN SERVICE8.8 mi
#7284138 kVKINGSPORT POWER COIN SERVICE9.0 mi
#24077138 kVKINGSPORT POWER COIN SERVICE4.9 mi
#37106138 kVKINGSPORT POWER COIN SERVICE4.9 mi
#48550138 kVKINGSPORT POWER COIN SERVICE4.5 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of EDENS RIDGE, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near EDENS RIDGE substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
NAGELSubstation-AdjacentVAScott County500 kV1,000 MW3.7 yrs78.2
BROADFORD (765 KV)Substation-AdjacentTNSullivan County500 kV1,000 MW3.7 yrs77.9
PHILLIPS BENDSubstation-AdjacentTNHawkins County500 kV1,000 MW3.7 yrs77.2
SULLIVANSubstation-AdjacentTNSullivan County500 kV1,000 MW3.7 yrs74.7
Greenfield (PHILLIPS BEND - NAGEL)GreenfieldVAScott County500 kV1,000 MW3.7 yrs73.9
Greenfield (SULLIVAN - NAGEL)GreenfieldTNHawkins County500 kV1,000 MW3.7 yrs73.1
Greenfield (SULLIVAN - NAGEL)GreenfieldTNSullivan County500 kV1,000 MW3.7 yrs72.4
HILLSubstation-AdjacentVAScott County138 kV100 MW3.7 yrs71.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.