WOODSDALE

Substation

Ohio · DUKE ENERGY

Max voltage
345
kV

WOODSDALE is an electric transmission substation in Ohio, operated by DUKE ENERGY. It is classified as high-voltage (345 kv) and connects 4 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage345 kV
Voltage classHigh-voltage (345 kV)
Connected lines4

Ownership & operation

OperatorDUKE ENERGY
StateOhio
Coordinates39.4506, -84.4615

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#1116345 kVDUKE ENERGYIN SERVICE4.7 mi
#34494345 kVDUKE ENERGYIN SERVICE4.8 mi
#65038345 kV0.3 mi
#65039345 kV0.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of WOODSDALE, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near WOODSDALE substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN113763Substation-AdjacentOHHamilton County345 kV600 MW3.2 yrs78.5
UNKNOWN113019Substation-AdjacentOHWarren County345 kV600 MW3.2 yrs78.5
TAP137571Substation-AdjacentOHWarren County345 kV600 MW3.2 yrs78.3
TERMINALSubstation-AdjacentOHHamilton County345 kV600 MW3.2 yrs78.3
FOSTERSubstation-AdjacentOHWarren County345 kV600 MW3.2 yrs77.8
TAP137572Substation-AdjacentOHWarren County345 kV600 MW3.2 yrs77.6
WOODSDALESubstation-AdjacentINDearborn County345 kV600 MW3.0 yrs77.4
WOODSDALESubstation-AdjacentOHButler County345 kV600 MW3.2 yrs77.4

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WOODSDALE substation, Ohio. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.