HILLCREST SOLAR

Substation

Ohio · AMERICAN ELECTRIC POWER CO., INC

Max voltage
345
kV

HILLCREST SOLAR is an electric transmission substation in Ohio, operated by AMERICAN ELECTRIC POWER CO., INC. It is classified as high-voltage (345 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage345 kV
Min voltage345 kV
Voltage classHigh-voltage (345 kV)
Connected lines2

Ownership & operation

OperatorAMERICAN ELECTRIC POWER CO., INC
Co-ownerDUKE ENERGY
StateOhio
Coordinates38.9726, -83.9708

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#28753345 kVAMERICAN ELECTRIC POWER CO., INCIN SERVICE32.8 mi
#37134345 kVDUKE ENERGYIN SERVICE26.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of HILLCREST SOLAR, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near HILLCREST SOLAR substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
TAP137571Substation-AdjacentOHWarren County345 kV600 MW3.2 yrs78.3
FOSTERSubstation-AdjacentOHWarren County345 kV600 MW3.2 yrs77.8
TAP137572Substation-AdjacentOHWarren County345 kV600 MW3.2 yrs77.6
BECKJORDSubstation-AdjacentKYCampbell County345 kV600 MW3.2 yrs77.3
UNKNOWN113020Substation-AdjacentOHWarren County345 kV600 MW3.2 yrs75.7
SILVER GROVESubstation-AdjacentKYCampbell County345 kV600 MW3.2 yrs73.3
TAP137604Substation-AdjacentOHHamilton County138 kV100 MW3.2 yrs72.5
PIERCESubstation-AdjacentOHClermont County345 kV600 MW3.2 yrs72.5

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for HILLCREST SOLAR substation, Ohio. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.