TAP160729

Substation

North Dakota

Max voltage
115
kV

TAP160729 is an electric transmission substation in North Dakota. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

Operator not catalogued for this substation.

Coordinates47.4298, -102.5025

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#5983115 kVIN SERVICE6.2 mi
#5984115 kVIN SERVICE0.0 mi
#6043115 kVIN SERVICE5.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP160729, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP160729 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
REDSubstation-AdjacentNDDunn County345 kV600 MW1.4 yrs77.6
Greenfield (CHARLIE CREEK - ANTELOPE VALLE)GreenfieldNDDunn County345 kV600 MW1.4 yrs70.3
UNKNOWN160730Substation-AdjacentNDDunn County115 kV100 MW1.4 yrs68.6
Greenfield (CHARLIE CREEK - ANTELOPE VALLE)GreenfieldNDMercer County345 kV600 MW1.4 yrs68.5
UNKNOWN160726Substation-AdjacentNDDunn County115 kV100 MW1.4 yrs68.5
Greenfield (ANTELOPE VALLEY STATION - RED)GreenfieldNDMercer County345 kV600 MW1.4 yrs68.4
TAP160729Substation-AdjacentNDDunn County115 kV100 MW1.4 yrs67.9
Greenfield (CHARLIE CREEK - ANTELOPE VALLE)GreenfieldNDDunn County345 kV600 MW1.4 yrs67.9

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP160729 substation, North Dakota. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.