TAP160697

Substation

North Dakota

Max voltage
230
kV

TAP160697 is an electric transmission substation in North Dakota. It is classified as high-voltage (230 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage230 kV
Voltage classHigh-voltage (230 kV)
Connected lines3

Ownership & operation

Operator not catalogued for this substation.

Coordinates47.5139, -100.7543

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#5714230 kVIN SERVICE0.1 mi
#16675230 kVIN SERVICE2.8 mi
#17194230 kVIN SERVICE72.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP160697, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP160697 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN133152Substation-AdjacentNDOliver County230 kV300 MW1.4 yrs75.4
TAP160697Substation-AdjacentNDSheridan County230 kV300 MW1.4 yrs73.3
Greenfield (GRAND FORKS - CENTER 345KV SWI)GreenfieldNDOliver County345 kV600 MW1.4 yrs72.7
MCHENRYSubstation-AdjacentNDMcLean County230 kV300 MW1.4 yrs72.5
Greenfield (GROTON - LELAND OLDS)GreenfieldNDOliver County345 kV600 MW1.4 yrs71.9
Greenfield (COAL CREEK - DICKINSON)GreenfieldNDOliver County400 kV600 MW1.4 yrs71.8
Greenfield (COAL CREEK - DICKINSON)GreenfieldNDOliver County400 kV600 MW1.4 yrs71.8
Greenfield (GRAND FORKS - CENTER 345KV SWI)GreenfieldNDOliver County345 kV600 MW1.4 yrs71.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP160697 substation, North Dakota. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.