WATEREE HYDRO

Substation

North Carolina · DUKE ENERGY CAROLINAS, LLC

Max voltage
115
kV

WATEREE HYDRO is an electric transmission substation in North Carolina, operated by DUKE ENERGY CAROLINAS, LLC. It is classified as sub-transmission (115 kv) and connects 5 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage100 kV
Voltage classSub-transmission (115 kV)
Connected lines5

Ownership & operation

OperatorDUKE ENERGY CAROLINAS, LLC
Coordinates34.3347, -80.7023

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#47093115 kVIN SERVICE5.0 mi
#58192100 kVDUKE ENERGY CAROLINAS, LLCIN SERVICE19.9 mi
#58193100 kVDUKE ENERGY CAROLINAS, LLCIN SERVICE19.9 mi
#64770100 kV0.1 mi
#64771100 kVIN SERVICE5.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of WATEREE HYDRO, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near WATEREE HYDRO substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN117533Substation-AdjacentSCRichland County230 kV300 MW4.3 yrs72.1
TAP142264Substation-AdjacentSCRichland County230 kV300 MW4.3 yrs71.2
UNKNOWN117539Substation-AdjacentSCRichland County230 kV300 MW4.3 yrs70.8
CAMDENSubstation-AdjacentSCKershaw County230 kV300 MW4.3 yrs69.0
UNKNOWN157677Substation-AdjacentSCRichland County115 kV100 MW4.3 yrs68.8
Rocky CreekBrownfieldSCLancaster28 MW68.7
UNKNOWN152841Substation-AdjacentSCRichland County115 kV100 MW4.3 yrs68.0
TAP150320Substation-AdjacentSCRichland County115 kV100 MW4.3 yrs68.0

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WATEREE HYDRO substation, North Carolina. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.