HILLTOP

Substation

North Carolina

Max voltage
100
kV

HILLTOP is an electric transmission substation in North Carolina. It is classified as distribution (69–115 kv) and connects 10 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage100 kV
Min voltage100 kV
Voltage classDistribution (69–115 kV)
Connected lines10

Ownership & operation

Operator not catalogued for this substation.

Coordinates35.2812, -81.2970

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#770100 kVIN SERVICE8.8 mi
#5094100 kVIN SERVICE0.1 mi
#6597100 kVIN SERVICE8.8 mi
#20127100 kVIN SERVICE8.4 mi
#26033100 kVIN SERVICE0.1 mi
#34583100 kVIN SERVICE4.2 mi
#35977100 kVIN SERVICE8.4 mi
#45858100 kVIN SERVICE5.0 mi
#47138100 kVIN SERVICE5.0 mi
#50371100 kVIN SERVICE4.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of HILLTOP, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near HILLTOP substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
MCGUIRESubstation-AdjacentNCMecklenburg County500 kV1,000 MW3.7 yrs81.1
CLEVELAND CNTY GENERATING FACILITYSubstation-AdjacentSCCherokee County230 kV300 MW4.3 yrs74.3
SHELBY TIESubstation-AdjacentNCCleveland County230 kV300 MW3.7 yrs73.9
Greenfield (UNKNOWN111199 - MCGUIRE)GreenfieldNCGaston County500 kV1,000 MW3.7 yrs73.5
Greenfield (UNKNOWN111199 - MCGUIRE)GreenfieldNCGaston County500 kV1,000 MW3.7 yrs73.0
WOODLAWNSubstation-AdjacentNCMecklenburg County230 kV300 MW4.3 yrs72.3
TAP169820Substation-AdjacentNCMecklenburg County230 kV300 MW4.3 yrs71.4
CATAWBA 230KV SWITCHING STATIONSubstation-AdjacentSCYork County230 kV300 MW4.3 yrs71.3

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.