EVERETTS

Substation

North Carolina · VIRGINIA ELECTRIC & POWER CO

Max voltage
230
kV

EVERETTS is an electric transmission substation in North Carolina, operated by VIRGINIA ELECTRIC & POWER CO. It is classified as high-voltage (230 kv) and connects 5 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage230 kV
Voltage classHigh-voltage (230 kV)
Connected lines5

Ownership & operation

OperatorVIRGINIA ELECTRIC & POWER CO
Coordinates35.9540, -77.0367

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#5928230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE22.3 mi
#9899230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE22.6 mi
#15964230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE13.4 mi
#56872230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE15.7 mi
#56897230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE32.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of EVERETTS, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near EVERETTS substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
TAP148198Substation-AdjacentNCHertford County230 kV300 MW4.3 yrs63.7
EVERETTSSubstation-AdjacentNCBertie County230 kV300 MW4.3 yrs63.0
UNKNOWN169539Substation-AdjacentNCBertie County230 kV300 MW4.3 yrs62.5
UNKNOWN111406Substation-AdjacentNCNorthampton County230 kV300 MW4.3 yrs62.3
EARLEYSSubstation-AdjacentNCHertford County230 kV300 MW4.3 yrs62.0
TAP148199Substation-AdjacentNCHertford County230 kV300 MW4.3 yrs61.9
UNKNOWN111623Substation-AdjacentNCWashington County230 kV300 MW4.3 yrs61.8
Greenfield (TAP148198 - EARLEYS)GreenfieldNCHertford County230 kV300 MW4.3 yrs60.4

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EVERETTS substation, North Carolina. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.