BUZZARD ROOST

Substation

North Carolina · DUKE ENERGY CAROLINAS, LLC

Max voltage
100
kV

BUZZARD ROOST is an electric transmission substation in North Carolina, operated by DUKE ENERGY CAROLINAS, LLC. It is classified as distribution (69–115 kv) and connects 4 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage100 kV
Min voltage100 kV
Voltage classDistribution (69–115 kV)
Connected lines4

Ownership & operation

OperatorDUKE ENERGY CAROLINAS, LLC
Coordinates34.1690, -81.9026

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#28010100 kVIN SERVICE1.8 mi
#64875100 kVDUKE ENERGY CAROLINAS, LLCIN SERVICE16.2 mi
#64876100 kVIN SERVICE2.6 mi
#64877100 kV0.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of BUZZARD ROOST, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near BUZZARD ROOST substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
TAP142095Substation-AdjacentSCSaluda County115 kV100 MW3.7 yrs69.8
TAP141834Substation-AdjacentSCEdgefield County115 kV100 MW3.7 yrs69.5
UNKNOWN116729Substation-AdjacentSCEdgefield County115 kV100 MW3.7 yrs67.6
Buzzard RoostBrownfieldSCGreenwood15 MW67.0
UNKNOWN117344Substation-AdjacentSCSaluda County115 kV100 MW3.7 yrs67.0
TAP142130Substation-AdjacentSCSaluda County115 kV100 MW3.7 yrs65.1
UNKNOWN116730Substation-AdjacentSCSaluda County230 kV300 MW4.3 yrs65.0
TAP141854Substation-AdjacentSCMcCormick County115 kV100 MW4.3 yrs64.4

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for BUZZARD ROOST substation, North Carolina. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.